This book represents a synthesis of research findings on energy in remote rural areas in East Nusa Tenggara in Indonesia, demarcating a localised understanding of electricity issues that are relevant to similar community profiles in other developing countries, which are facing similar challenges. The authors discuss several key issues relating to electricity access in the Indonesian context, such as government energy expenditure and policies for geothermal development. The book also presents empirical estimates of the social effects of electricity access. In focusing on an underdeveloped area in eastern Indonesia affected by innumerable problems relating to poverty, the book contributes to related discussions on the first Sustainable Development Goal in proposing possibilities for poverty reduction vis-à-vis improved energy infrastructure. It demonstrates the impact of electricity access on people's welfare. Co-published with the Indonesia Institute of Science (LIPI), this updated edition is a valuable reference for policymakers and scholars interested in the electricity sector in Indonesia and rural areas in developing countries elsewhere. It appeals to specialists researching and working in the energy sector and is also interested in scholars and practitioners focused on sustainable development and Indonesian policymaking more broadly.
Economic Research Center
Gedung Widya Graha LIPI
Indonesian Institute of Sciences (LIPI)
Kota Jakarta Selatan
Jakarta, Indonesia
Research Center for Area Studies
Indonesian Institute of Sciences (LIPI)
Jakarta, Indonesia
ISEAS Yusof Ishak Institute
Singapore, Singapore
Economic Research Center
Gedung Widya Graha LIPI
Indonesian Institute of Sciences (LIPI)
Kota Jakarta Selatan
Jakarta, Indonesia
Economic Research Center
Gedung Widya Graha LIPI
Indonesian Institute of Sciences (LIPI)
Kota Jakarta Selatan
Jakarta, Indonesia
Al Mohtad, I. (2006). Remote area power supply systems (RAPSS). Himala- yan Small Hydropower Summit. October 12–13, 2006.
Central Agency of Statistics (BPS). (2019a). Pertumbuhan Ekonomi Indonesia Triwulan IV-2018.
Central Agency of Statistics (BPS). (2019b). Profil kemiskinan di Indonesia September 2018.
International Energy Agency (IEA). (2018). World energy outlook 2018. International Press.
Kanagawa, M., & Nakata, T. (2008). Assessment of access to electricity and the socio-economic
impacts in rural areas of developing countries. Energy Policy, 36, 2016–2029.
Khandker, S. R., Barnes, D. F., & Samad, H. A. (2013). Welfare impacts of rural electrification: A
panel data analysis from Vietnam. Economic Development and Cultural Change, 61(3), 659–692.
Munasinghe, M. (1988). Rural electrification: International experience and policy in Indonesia.
Bulletin of Indonesia Economic Studies, 24(2), 87–105.
Peng, W., & Pan, J. (2006). Rural electrification in China: History and institution. China & World
Economy, 14(1), 71–84.
PLN. (2014). Status, target, dan tantangan program elektrifikasi nasional dan investasi energi
terbarukan. A paper presented at FGD conducted by LIPI on July 21, 2014.
PLN. (2018). Statistik PLN 2018. Jakarta: PT PLN.
Reiche, K., Covarrubias, A., & Martinot, E. (2000). Expanding electricity access to remote areas:
Off-grid rural electrification in developing countries. World Power.
Republic of Indonesia. (2007). Energi. Undang-undang No. 30 Tahun 2007 tentang Energi.
Republic of Indonesia. (2009). Ketenagalistrikan. Undang-undang No. 30 Tahun 2009 tentang
Ketenagalistrikan.
Republic of Indonesia. (2014). Panas bumi. Undang-undang Republik Indonesia No. 21 Tahun 2014 tentang Panas Bumi.
Sambodo, M. T., Fuady, A. H., Negara, S. D., Handoyo, F. W., & Mychelisda, E. (2013). Laporan
Penelitian Model dan Strategi Pengembangan Sektor Ketenagalistrikan di Daerah dalam Upaya Pengentasan Kemiskinan. Jakarta: Pusat Penelitian Kependudukan.
Yuli. (2011, 9 April). Bangun listrik tenaga surya di 100 pulau. Kompas. com. Accessed on May
from http://bisniskeuangan.kompas.com/read/2011/04/09/07431522/bangun.listrik.tenaga.
surya.di.100.pulau
Amalo, P. (2020, September 6). The first Bayu power plant will be built in NTT. Pembangkit
Listrik Tenaga Bayu Pertama akan Dibangun di NTT. Retrieved September 6, 2020,
ANTARA News. (2019, December 10). PLN NTT is targeting to build geothermal power plants
of up to 115 MW. PLN NTT targetkan bangun pembangkit panas bumi hingga 115 MW.
Retrieved September 5, 2020, from https://www.antaranews.com/berita/1202135/pln-ntt-targetkan-bangun-pembangkit-panas-bumi-hingga-115-mw
Bappeda, Manggarai District. (2014). The general information about electricity development in
Manggarai District. Presentasi mengenai gambaran umum pembangunan kelistrikan di Kab.
Manggarai, June 2014.
BPPT. (2010).Oceanwave power plant Prototipe Trial. UjiCoba prototipe pembangkit listrik tenaga arus laut. Jakarta: BPPT.
BPS. (2013). Satarmese district in 2013 figures. Kecamatan Satarmese dalam angka 2013. BPS of Manggarai District, East Nusa Tenggara.
BPS of East Nusa Tenggara. (2014). East Nusa Tenggara in 2014 figures. Nusa Tenggara Timur
dalam angka 2014.
BPS. (2019). East Nusa Tenggara province in figures 2019. Provinsi Nusa Tenggara Timur Dalam Angka 2019.
BPS Provinsi NTT. (2018a). Total Population by age group and regency/City in East Nusa Tenggara Province, 2017. Jumlah Penduduk Menurut Kelompok Umur dan Kabupaten/Kota di Provinsi Nusa Tenggara Timur, 2017. Retrieved September 5, 2020, from https://ntt.bps.go.id/dynamictable/2020/06/25/1481/jumlah-penduduk-menurut-kelompok-umur-dan-kabupaten-kota-di-provinsi-nusa-tenggara-timur-2017.html
BPS Provinsi NTT. (2018b, January 30). Projected population growth rate of East Nusa Tenggara Province. Proyeksi Laju Pertumbuhan Penduduk Provinsi Nusa Tenggara Timur, 2011–2020. Retrieved September 5, 2020, from https://ntt.bps.go.id/dynamictable/2016/11/23/361/proyeksilaju-
pertumbuhan-penduduk-provinsi-nusa-tenggara-timur-2011-2020.html
Budiartie, G. (2019, April 12). This Eastern heaven of Indonesia will be bright with solar
power. Surga Timur RI Ini Bakal Terang dengan Tenaga Surya. Retrieved September 7, 2020,
Directorate of Geothermal, Directorate General of EBTKE, Center for Mineral, Coal and
Geothermal, B. G. (2017). Indonesia’s Geothermal Potential Volume 2. Potensi Panas Bumi
Indonesia Jilid 2. Jakarta.
Government Province of NTT. (2010). Management of coal and mineral mining. Pengelolaan
pertambangan batu bara dan mineral. Perda ProvinsiNTT No. 8 Tahun 2010 tentang Pengelolaan Pertambangan Batu Bara dan Mineral.
Indrawan, R. (2020, March 9). PLTS Labuan Bajo 70 MW Phase I is targeted to be completed in
PLTS Labuan Bajo 70 MW Tahap I Ditargetkan Rampung 2022. Retrieved September
, 2020, from https://www.dunia-energi.com/plts-labuan-bajo-70-mw-tahap-i-ditargetkan-ram
pung-2022/
Januwarsono, S. (2010). Electricity system development planning as an effort to meet the needs of electric energy in the province of NTT. Perencanaan pembangunan sistem kelistrikan sebagai upaya pemenuhan kebutuhan energi listrik di provinsi NTT.
Lewokeda, A. (2019, February 21). The use of electrical energy in NTT grew by around 8.4%.
Pemakaian energi listrik di NTT tumbuh sekitar 8,4 persen. ANTARA News Kupang, Nusa Tenggara Timur. Retrieved from https://kupang.antaranews.com/berita/14139/pemakaian-energi-listrik-di-ntt-tumbuh-sekitar-84-persen
Likadja, F. J. (2012).Analysis of the implementation of the national energy policy on energy demand in the province of East Nusa Tenggara using leap software. Analisis penerapan kebijakan energi nasional terhadap permintaan energi di provinsi Nusa tenggara timur menggunakan perangkat lunak leap. Prosiding Seminar Proceeding Nasional Sains dan Teknologi, Vol. 2 Bidang Teknik,
T-181–T-187. Bali: Undana Press.
Likadja, F. J. (2014). Implementation of conservation and diversification policies on the availability
of electrical energy in the province of East Nusa Tenggara. Penerapan kebijakan konservasi
dan diversifikasi terhadap ketersediaan energi listrik di provinsi Nusa Tenggara Timur. Nusa
Cendana Kupang University. Retrieved October 15, 2014 from http://ipenconsulting.com/yahoo_
site_admin/assets/docs/P15_FLikadja_Re-view_of_RE_Policy_in_NTT.4825204.pdf
Ministry of ESDM. (2015). 2015 EBTKE Statistics. Statistik EBTKE 2015. Jakarta: Ministry of
ESDM, Directorate General of New, Renewable Energy, and Energy Conservation.
Ministry of ESDM. (2016). Development of new renewable energy-based power plants in East
Nusa Tenggara Province, Fiscal Year. Pembangunan Pembangkit Listrik Berbasis Energi Baru
Terbarukan di Provinsi Nusa Tenggara Timur Tahun Anggaran 2016–2017. Jakarta: Ministry of
ESDM, Directorate General of New, Renewable Energy, and Energy Conservation.
Ministry of ESDM RI. (2018, April 2). Theminister of energy and mineral resources visits the location of the construction of a sea current power plant in the Larantuka Strait. Menteri ESDM Tinjau Lokasi Pembangunan Pembangkit Listrik Arus Laut di Selat Larantuka. Retrieved September 5, 2020, from http://ebtke.esdm.go.id/post/2018/04/02/1924/menteri.esdm.tinjau.lokasi.pemban
gunan.pembangkit.listrik.arus.laut.di.selat.larantuka
Ministry of ESDM RI. (2020, February 17). The government continues to improve PLTS development. Pemerintah Terus Perbaiki Tata Kelola Pembangunan PLTS. Retrieved September 7, 2020, from http://ebtke.esdm.go.id/post/2020/02/17/2476/pemerintah.terus.perbaiki.tata.kelola.
pembangunan.plts
PLN Sub-rayon Ruteng. (2014). 2013 realization in generating sector. Realisasi 2013 bidang
pembangkit. Jakarta: PT PLN.
PLN. (2013a). Electricity supply business plan. Rencana usaha penyediaan tenaga listrik PT PLN 2013–2022. Jakarta: PLN.
PLN. (2013b). PLN Statistics 2013. Statistik PLN 2013. Jakarta: PLN.
PLN. (2014a). Historical development of the Ulumbu geothermal field. Historical pengembangan lapangan panas bumi Ulumbu. Jakarta: PT PLN.
PLN. (2014b). Determination of the tariff adjustment for electricity (tariff adjustment) in November 2014. Penetapan penyesuaian tarif tenaga listrik (tariff adjustment) bulan November 2014. Accessed on November 5, 2014 from http://www.pln.co.id/dataweb/TTL2014/07_Tariff%20A
djusment%20Nopem-ber%202014.jpg
Republic of Indonesia. (2007). Electricity. Indonesian Law No. 30/2009 about Electricity.
Ketenagalistrikan. Undang-undang No. 30 tahun 2009 tentang ketenagalistrikan
Setiawan, S. (2012). Geothermal energy within the MP3EI framework: Analysis of prospects,
constraints and policy support. Energi panas bumi dalam kerangka MP3EI: Analisis terhadap
prospek, kendala, dan dukungan kebijakan. Jurnal Ekonomi dan Pembangunan, XX (1).
Setiawan, F., Hernandhy, E., & Qisthy, A. (2011). Renewable energy development by identifying
cross-Indonesian flows in Eastern Indonesia. Pengembangan energi terba- rukan dengan
identifikasi arus lintas Indonesia di Wilayah Timur Indonesia. Bandung: Unpad.
Simorangkir, E. (2016, September 22). Take a peek at the Solar Power Plant. Mengintip Pembangkit Listrik Tenaga Surya Terbesar di RI.Retrieved September 6, 2020, from https://finance.detik.com/energi/d-3351258/mengintip-pembangkit-listrik-tenaga-surya-terbesar-di-ri
Susandi, A. (2012).Wind data processing and wind energy potential in Indonesia. Pengolahan data angin dan potensi energi angin di Indonesia. Retrieved November 4, 2014, from www.armisusandi.com/energi/P5_ME4132.ppt.
Agustina, C. D., Ahmad, E., Nugroho, D., & Siagian, H. (2012). Political economy of natural
resource revenue sharing in Indonesia. Jakarta. Accessed on November 12, 2014 from http://
www.lse.ac.uk/asiaResearchCen-tre/_files/ARCWP55-AgustinaAhmadNugrohoSiagian.pdf
Department of ESDM, Manggarai District. (2014). Laporan tentang PLTPB Ulumbu, Kabupaten
Manggarai, Nusa Tenggara Timur. Manggarai.
Department of Water and Mining Resources. (2011). Garut regency geothermal investment
opportunities. Kabupaten Garut.
Directorate of Geothermal. (2013). Pengembangan panas bumi Indonesia. Kementerian Energi dan Sumber Daya Mineral Republik Indonesia.
Directorate of Geothermal. (2014). Pengembangan sektor panas bumi dalam upaya pengentasan pemiskinan.
Minister of Energy andMineral Resources of the Republic of Indonesia. (2014).Ministerial Decree of Energy andMineral Resources No. 2363K/30/ MEM/2014 on Geothermal Preliminary Survey
Assignment to PLN in Ulumbu Area, Manggarai District, NTT Province.
PLN. (2014). Historical Pengembangan Lapangan Panas Bumi Ulumbu (Presentation materials, unpublished).
Republic of Indonesia. (1999). Pemerintah daerah. Undang-undang No. 22 tahun 1999 tentang
Pemerintahan Daerah.
Republic of Indonesia. (2003). Panas Bumi. Undang-undang Republik Indonesia No. 27 tahun 2003
tentang Panas Bumi.
Republic of Indonesia. (2004). Pemerintah daerah. Undang-undang No. 32 tahun 2004 tentang
Pemerintahan Daerah.
Republic of Indonesia. (2007). Energi. Undang-undang Republik Indonesia No. 30 tentang Energi.
Republic of Indonesia. (2009). Ketenagalistrikan. Undang-undang Republik Indonesia No. 30
tentang Ketenagalistrikan.
Republic of Indonesia. (2014). Pemanfaatan panas bumi. Undang-undang No. 21 tahun 2014 tentang Pemanfaatan Panas Bumi.
Republic of Indonesia (2014). Pemerintahan daerah. Undang-undang No. 23 tahun 2014 tentang Pemerintahan Daerah.
Sambodo, M. T., Fuady, A. H., Negara, S. N., Handoyo, F., & Mychelisda, E. (2014). Laporan
Penelitian Model dan Strategi Pengembangan Sektor Ke- tenagalistrikan di Daerah dalam Upaya Pengentasan Kemiskinan. Jakarta: Pusat Penelitian Kependudukan.
Alkire, S., Conconi, A., & Seth, S. (2014). Multidimensional poverty index 2014: Brief . Accessed
on August 20, 2014 from http://www.ophi.org.uk/wp-content/uploads/Global-MPI-2014-Brief-
Methodological-Note-and-Results.pdf
BPS. (1984). Dampak listrik masuk desa dan perusahaan listrik non-PLN: Provinsi Sumatera Utara dan Sulawesi Selatan. Jakarta: BPS.
Dakung, S., Sitanggang, H.,Manan, F. N.,Wahyuningsih, D., &Waluyo, H. (1990). Dampak listrik
masuk desa di Desa Cisadane, Keca- matan Cibadak Kabupaten Sukabumi. Jakarta: Departemen Pendidikan danKebudayaan,Direktorat JenderalKebudayaan,Direktorat Sejarah dan Nilai Tradisional Proyek Inventarisasi dan Pembinaan Nilai-Nilai Budaya. Departemen Pendidikan dan Kebudayaan.
ESDM. (2020). Statistik Ketenagalistrikan 2019. Jakarta: Sekretariat Jenderal Ketenagalistrikan.
Gertler, P. J., Martinez, S., Premand, P., Rawlings, L. B., & Veermeersc, C. M. J. (2011). Impact
evaluation in practice. The World Bank.
IEA. (2013). World energy outlook 2013. OECD/IEA.
Khandker, S. R., Barnes, D. F., & Samad, H. A. (2013). Welfare impacts of rural electrification: A
panel data analysis from Vietnam. Economic Development and Cultural Change, 61(3), 659–692.
Laskari, F. (2012). Lisder Bukan Tanggung Jawab PLN Rayon Sungailiat. Tribunnews.com.
Accessed on May 2013 from http://bangka.tribunnews.com/2012/07/30/lisdes-bukan-tanggungjawab-pln-rayon-sungailiat
PLN. (2012). Rencana usaha penyediaan tenaga listrik PT. PLN 2013–2022. Jakarta; PT. PLN.
PLN. (2014). Statistik PLN. Jakarta: PT. PLN.
Republic of Indonesia. (2007). Energi. Undang-undang Republik Indonesia No. 30 tentang Energi.
Sambodo, M. T., Fuady, A. H., Negara, S. N., Handoyo, F., & Mychelisda, E. (2014). Laporan
penelitian model dan strategi pengembangan sektor ketenagalistrikan di daerah dalam upaya
pengentasan kemiskinan. Jakarta: Pusat Penelitian Kependudukan.
Department of Mining and Energy (DPE). (2000). 55 years of mining and energy development.
Departemen Pertambangan dan Energi.
ESDM. (2020a). Statistik Ketenagalistrikan 2019. Direktorat Jenderal Ketenagalistrikan
ESDM. (2020b). Handbook of energy&economic statistics of Indonesia 2019. Kementerian Energi dan Sumber Daya Mineral.
International Energy Agency (IEA). (2014). World energy outlook 2014. IEA Publications.
International Energy Agency (IEA). (2019). Energy security in ASEAN +6. IEA Publications.
Ministry of ESDM. (2013). Draft general plan of electricity (RUKN) 2012–2031. Accessed on
November 1, 2014 from www.energy-indonesia.com/02electrcitylaw/0130213RUKN.pdf
Ministry of ESDM. (2014a). The Minister Regulation No. 3/2014 on Technical Guidance on the
Use of Special Allocation Fund for Rural Energy Budget Year 2014. Accessed on November 2,
from http://prokum.esdm.go.id/permen/2014/Permen%20ESDM%2003%202014.pdf
Ministry of ESDM. (2014b). DAK untuk listrik perdesaan. Accessed on November 2,
from http://esdm.go.id/news-archives/323-energi-baru-dan-terbarukan/5265-dak-untuk-listrik-perdesaan.html.
Mulyadi, A. (2011, Juli 15). KPK tahan pejabat ESDM. Kompas.com. Accessed on November 13,
from http://nasional.kompas.com/read/2011/07/15/2015544/KPK.Tahan.Pejabat.ESDM
Minister of Energy and Mineral Resources of the Republic of Indonesia. (2014). The Minister
Regulation of Energy and Mineral Resources No. 3/2014 on Technical Guidance on the Use of
Special Allocation Fund for Rural Energy Budget Year 2014.
Mujayatno, A. (2013). Pemerintah gratiskan listrik 500 KK miskin Nunukan. Accessed on
November 1, 2014 from http://www.kaltaraprov.go.id/news-view/465/pemerintah.gratiskan.listrik.500.kk.miskin.nunukan.html
PLN. (2013). Rencana Usaha Penyediaan Tenaga Listrik PT PLN (Persero) 2013–2022. PT. PLN.
PLN. (2014). PLN statistik 2013. PT. PLN.
Republic of Indonesia. (2007). Energi. Undang-Undang Republik Indonesia No. 30 tentang Energi.
Republic of Indonesia. (2009). Ketenagalistrikan. Undang-Undang Republik Indonesia No. 30
tentang Ketenagalistrikan.
Republic of Indonesia. (2014a). The Government Regulation No. 43/2014 on the implementation of the Village Fund.
Republic of Indonesia. (2014b). Desa. Undang-Undang Republik Indonesia No. 6 tentang Desa.
Sambodo, M. T., Fuady, A. H., Negara, S. N., Handoyo, F., & Mychelisda, E. (2014). Laporan
Penelitian Model dan Strategi Pengembangan Sektor Ke- tenagalistrikan di Daerah dalam Upaya Pengentasan Kemiskinan. Jakarta: Pusat Penelitian Kependudukan.